Sector-32GurugramTehsil Sohna
HARERA ActiveNewRERA-GRG-1158-2022Registered 15 September 2022

Central Park The Orchard

Project Dossier · Prepared by KC Realty

A registered group-housing development. Everything below is read straight off the project's HARERA filing — land, FAR, cost stack, approvals and specifications. We publish the numbers first and the adjectives last.

4
Floors
4.13 acres
Land Area
Jun 2026
RERA Completion

Section 01 — Situation

The Filing At A Glance

This dossier reads the project's HARERA filing and nothing else — no brochure copy, no launch-day adjectives. Where we have done arithmetic on the filing, we say so and show the working.

RERA Registration
RERA-GRG-1158-2022

Received 15 September 2022. Project type: New.

RERA Completion
30 June 2026

The contractual outer date on the filing. Roughly a 4-year build from registration.

District & Tehsil
Gurugram · Sohna

Project address: Situated In Sector-32, Tehsil-sohna, Gurugram

Developer
St Patricks Realty Private Limited

CIN U45200HR2008PTC037964.

Section 02 — Inventory

Configurations & Pricing

The filing does not carry a unit-level floor-plan schedule for this project. We pull the unit-numbered price sheet directly from the developer on request.

What We Will Get You

Configuration, super and carpet area, floor-wise pricing and the full cost breakup including GST, PLC, parking and IFMS — on the specific unit you are considering.

Section 03 — Assessment

The Lens

We look at every asset through four questions before anything else. This is our reading of the filing — not the developer's brochure, and not a recommendation. Confirm everything against the live HARERA record before you commit capital.

01

Entry

The filing does not carry a published rate for this project. We will get you the current price sheet and benchmark it against the corridor before you make an offer.

02

Return

RERA completion is 30 June 2026. That is roughly a 4-year capital commitment from registration. The payment plan determines how much of your money is actually deployed, and when.

The filing consumes 2.64 of a permissible 2.64 FAR — about 100% of the allowable envelope. A high share of the permitted envelope is being used, which is what carries the unit count.

03

Risk

On the credit side, all 10 statutory approvals on the filing are recorded as already obtained, and every service NOC is approved. That is a cleaner-than-average entitlement position.

04

Exit

Your realistic exit windows are the construction-linked resale market between now and 2026, and the post-possession market thereafter. Both are decided by what else launches in this corridor in the interim — which is what our Section 04 tracking is for.

Diligence Cross-Checks We Ran

The cost stack reconciles. The declared cost heads sum to ₹43,540.14 L, exactly the declared estimated project cost. No unexplained gap.

Section 04 — Ground

The Micro-Market

Registered projects in the immediate belt, and where this one sits against them on rate. This is the band your resale will eventually be quoted inside. Where a rate is not published on a comparator's filing, we leave it blank rather than guess.

Central Park Bignonia Towers · Sector 32
₹20,000
Ashiana Anmol · Sector 33
₹11,000
Neighbouring Registered Projects
ProjectLocationRateConfigurationsStage
J 36 by J EstatesSector 36, SohnaNot publishedNewly Launched
Central Park Bignonia TowersSector 32, Sohna₹20,000 /sqft4 BHK 3 BHKEarly Stage Construction
Ashiana Anmol Phase 2 and Phase 3Sector 33, Sohna₹11,000 /sqft2 BHK 3 BHKReady To Move
Ashiana Anmol Phase IISector 33, Sohna₹11,000 /sqft2 BHK 3 BHKReady To Move
Ashiana AnmolSector 33, Sohna₹11,000 /sqft2 BHK 3 BHKReady To Move
Advik By ROFSector 36, SohnaNot publishedNewly Launched
Ganesh ComplexSohnaNot publishedNewly Launched
Aqva The ReserveSector 5, SohnaNot publishedNewly Launched
Central Park Flower Valley Phase IvSohnaNot publishedReady To Move

Section 05 — Terrain

Land, FAR & Density

More than one land figure appears across the filing. They are not contradictory — they measure different things — but you should know which one you are being quoted.

Total Licensed Land
47.759 acres

The full licensed holding — the envelope inside which future phases would sit.

Project Land Area
4.13 acres
Proposed FAR
2.64

Against a permissible 2.64 — about 100% of the allowable envelope consumed.

Permissible FAR
2.64

Headroom of 0.00 FAR remains unconsumed on the filed scheme.

Lifts
Schneider

Registered Parcel Versus Licensed Holding

This registration covers 4.127 acres of a 47.759-acre licensed holding. The balance land is not part of what you are buying into today and may carry further phases. Anything shown to you on a masterplan that sits outside the registered parcel is intent, not entitlement, until it is separately registered.

Section 06 — The Desk

The Promoter's Cost Stack

Every RERA filing carries the promoter's own estimate of what the project costs to build. Most buyers never read it. It tells you where the money actually goes.

Declared Project Cost — figures in ₹ lakhs
HeadAmount (₹ L)In ₹ CrShare of Project Cost
Land cost5,596.4755.9612.85%
Other cost5,706.9657.0713.11%
Apartment construction cost32,236.71322.3774.04%
Infrastructure cost0.000.000.00%
Estimated project cost43,540.14435.40100.00%
Observation 01

Where The Money Goes

Land is ₹56 Cr, or 12.85% of the declared cost, against 74.04% for apartment construction. On a Gurugram parcel that is not unusual, but it is the single most important number in the stack: it is what makes the headline rate structurally difficult to discount.

Observation 02

Read It Against The Licensed Land

The land cost sits against a 47.759-acre licensed holding while only the registered 4.127-acre parcel is covered here. Any per-unit cost you derive from this table therefore overstates the cost of the registered phase. Do not use it as a margin calculation.

Section 07 — Entitlement

Approvals, NOCs & Documents

The entitlement position is the part of a project that either exists or does not. On this filing every statutory approval is recorded as already obtained.

Statutory Approvals
ApprovalDateStatus
Dtcp License10-12-2021Obtained
Lc-iv10-12-2021Obtained
Layout Plan Approval13-12-2021Obtained
Forest NOC29-12-2021Obtained
Electricity Load Sanctioned19-03-2021Obtained
Loi24-09-2021Obtained
Br-iii29-12-2022Obtained
Service Estimate16-05-2022Obtained
Zoning Plan10-08-2022Obtained
Environment Clearance19-08-2022Obtained
Service NOCs
ServiceProviderStatus
RoadsNHAIApproved
Water SupplyHSVPPending
ElectricityDHBVNLPending
Sewage DisposalHSVPPending
Storm Water DrainageHSVPPending
Documents On The RERA Record
DocumentUploaded
Copy Of License Along With Schedule Of Land14-09-2022
Documents Relating To The Entry Of License And Collaboration Agreement In The Revenue Record14-09-2022
Zoning Plan14-09-2022
Non Default Certificate From A Chartered Accountant14-09-2022
Declaration Supported By Affidavit Duly Signed By The Promoter To Be Enclosed.15-09-2022
In Case Of Group Housing/ Commercial Sites, A Copy Of The Approved Site Plan15-09-2022
In Case Of Plotted Colony, The Latest Layout Plan15-09-2022
Cash Flow Statement Of The Proposed Project25-01-2023

We pull and read these documents for clients before a booking, rather than after.

Section 08 — Provision

Declared Facilities

These are the facilities committed on the RERA filing, reproduced with the exact status recorded against each. A committed facility is a contractual item; a rendering is not.

Section 09 — Build

Specifications On File

The construction specifications as declared to HARERA, reproduced without embellishment. Where the filing says N/A, we say N/A — those are the line items to negotiate or clarify in writing.

Construction Specifications

Flooring Details Of Various Parts Of House
Laminated Wooden Flooring / Marble
Wall Finishing Details
High Quality Designer Ceramic Tiles / Marble
Kitchen Details
Anti Skid /Vitrified Tiles / Marble
Bathroom Fittings
High Quality Designer Ceramic Tiles / Marble
Wood Work Etc
Laminated Wooden Flooring
Doors And Windos Frames
Flush Door With Vineer / Laminated Equivalent
Glass Work
UPVC With Toughened Glass
Electric Fittings
Modular Type
Conducting And Wiring Details
Frls (kei, Polycab, Anchor Or Equivalent)
Cupboard Details
Hmhdr Board
Water Storage
Water Tank
Lift Details
Schneider
External Glazings
UPVC With Toughened Glass
Windows/Glazings
UPVC With Toughened Glass
Main Doors
Flush Door With Vineer / Laminated Equivalent ,
Internal Doors
Flush Door With Vineer / Laminated Equivalent ,
Air Conditioning
Vrv
Electrical Fittings
As Per Is Codes
CNG Pipe Line
Not Applicable
Provision Of WIFI And Broadband Facility
As Per Availability
External Finishing/Colour Scheme
As Per Our Scheme
Doors
And Windos Frames Flush Door With Vineer / Laminated Equivalent

Section 10 — Queries

Straight Answers

The questions buyers actually ask, answered from the filing rather than from the brochure.

Where exactly is Central Park The Orchard?

The filing records the project address as Situated In Sector-32, Tehsil-sohna, Gurugram, in District Gurugram, Tehsil Sohna.

Is it RERA registered, and under what number?

Yes. It is registered with Haryana RERA under RERA-GRG-1158-2022, received 15 September 2022. We recommend you verify it yourself on the HARERA portal — we will walk you through the lookup if you have not done one before.

What is the possession timeline?

RERA completion is filed for 30 June 2026. That is the date the promoter is held to, not a marketing estimate. Confirm the current position against the live HARERA filing before you sign anything.

Are all the approvals in place?

On this filing every statutory approval is recorded as already obtained and every service NOC as approved. Approvals can nonetheless be varied or added to, so check the live record before booking.

Who is the developer?

The filing names St Patricks Realty Private Limited as the promoter (CIN U45200HR2008PTC037964).

Are home loans available?

Yes — home loan facilities are available from most major banks on HARERA-registered projects. We can point you to lenders who operate on this project. We are not a loan agent, we do not arrange finance and we do not assess your eligibility — sanction, rate and terms are entirely between you and the lender.

Where do my payments actually go?

Into the project's designated RERA account — never into anyone's general account. Under RERA, 70% of collections must sit in that designated account and can only be drawn against certified construction progress. Ask the developer for the account details in writing, and see the warning below before you transfer anything.

Always Pay Into The Designated Account

Under RERA, 70% of collections must sit in the project's designated account. Get those account details from the developer in writing, verify them directly on the HARERA portal before any transfer, and insist on a receipt that names the project and the registration number RERA-GRG-1158-2022.

We will never ask you to route money through us, and we will never send you revised account details by message or email. If you receive any such instruction claiming to be from us or from the developer, stop and call us before you act on it.

Recce

Walk It With Us

We will pull the unit-numbered price sheet, the full cost breakup including GST, PLC, parking and IFMS, the payment plan, the approved floor plans and the master plan — and we will read the RERA documents with you before you commit anything.

Your capital first. The honesty of our advice next. Our commission last.

Message Us On WhatsApp

No need to share PAN, bank details, salary slips or ID documents here — we will never ask for them by form.

Submitted to KC Realty (KiloCharlie Realty), HARERA registered real estate agent no. RC/HARERA/GGM/4668/4263/2026/703. We use these details to respond to your enquiry by phone, WhatsApp or email. If you decide to take a project forward, we share what the promoter needs to register your visit. We never sell or rent enquiry data. You can ask us to stop contacting you at any time; some records we are required by law to keep. Privacy Policy.

Enquiry Received

An advisor will be in touch within 24 hours with the Central Park The Orchard cost breakup.

Important notice — please read before relying on anything on this page

1. Source and method. The particulars set out on this page have been compiled from publicly available disclosures made in respect of this project under the Real Estate (Regulation and Development) Act, 2016 and the rules made thereunder, including the registration granted by the Haryana Real Estate Regulatory Authority under RERA-GRG-1158-2022 dated 15 September 2022. Figures expressly identified as computed — cost-share percentages, price reconciliations, density cross-checks, FAR consumption and comparator medians — are arithmetic worked out by KC Realty from those disclosures and are shown so that they may be independently checked. They are analytical observations, not statements of fact by the promoter.

2. No representation or warranty. This page is provided on an "as is" and "as available" basis, for general information only. KC Realty gives no representation, warranty, assurance or guarantee of any kind, express or implied, as to the accuracy, completeness, currency, reliability or suitability of any content, and expressly disclaims all such warranties to the fullest extent permitted by law. Public records are amended and may contain errors or omissions; content may become out of date at any time and KC Realty is under no obligation to update it.

3. Not an offer. Nothing on this page constitutes an offer, an invitation to offer, a solicitation, an advertisement, a prospectus or any part of a contract, and no contractual, fiduciary or advisory relationship arises from your accessing or relying on it. No statement here forms part of, varies, supplements or overrides any agreement between you and the promoter.

4. Independent verification is your responsibility. Prices, rates, availability, configurations, areas, layouts, plans, specifications, approvals, amenities and timelines are indicative, subject to change without notice and subject to statutory approvals. All prices are base selling price only; GST, PLC, parking, IFMS, stamp duty, registration and all other statutory and incidental charges are additional. Areas stated are as declared and may be super, carpet or built-up as indicated; where carpet area is derived it is marked as such. Before making any booking, payment or financial commitment you must satisfy yourself independently by inspecting the official records of the Haryana Real Estate Regulatory Authority, the sanctioned plans and approvals, the allotment letter and the builder-buyer agreement, and by taking your own legal, financial and tax advice. You should rely solely on those documents and not on this page.

5. No liability. To the maximum extent permitted by law, KC Realty, its proprietor, employees and associates accept no liability whatsoever for any loss, damage, cost or expense — whether direct, indirect, incidental, special, consequential or for loss of profit or opportunity — arising out of or in connection with any use of, or reliance on, this page or any error or omission in it.

6. Independent agent; not the promoter. KC Realty (KiloCharlie Realty) is an independent real estate agent registered with the Haryana Real Estate Regulatory Authority, Gurugram. It is not the promoter, developer, builder, owner, landowner or joint-development partner of this project, and is not authorised to make any representation, warranty or commitment on the promoter's behalf. Any such representation, if made, is not binding on the promoter. All payments must be made directly to the promoter in the project's designated RERA account by traceable banking channel; KC Realty does not collect, receive or hold buyer funds.

7. Not investment advice. Nothing on this page is investment, financial, tax, accounting or legal advice, or a recommendation to buy, sell or hold any property or other asset. KC Realty is not a registered investment adviser. Real estate carries risk, including construction delay, regulatory change and loss of capital. Past or prevailing prices are not indicative of future returns, and no return, rental, appreciation, buy-back or assured outcome of any kind is promised or implied.

8. Third-party marks. All project names, brand names, trademarks, service marks and logos referred to are the property of their respective owners and are used purely for identification and descriptive purposes. Their use does not imply any endorsement, affiliation, sponsorship or partnership. Comparative information about other projects is included for general market context only.

9. Governing law. This notice is governed by the laws of India, and the courts at Gurugram, Haryana shall have exclusive jurisdiction. If any part of this notice is held unenforceable, the remainder continues in effect. By continuing to use this page you accept this notice in full.

Project HARERA registration: RERA-GRG-1158-2022, available at the Authority's official website.

HARERA registered real estate agent: KC Realty (KiloCharlie Realty), registration no. RC/HARERA/GGM/4668/4263/2026/703. Registered with the Haryana Real Estate Regulatory Authority, Gurugram under section 9 of the Real Estate (Regulation and Development) Act, 2016.